Construction Activities
(A) Periodic updates of work progress, consultation activities and planned work schedules. The site must indicate the date of the last update and the frequency of the internet site updates.
Work Progress:
- Contract for constructing the pipeline has been awarded to Mitchell Australasia for $28M
- Murray River power line has been constructed by Country Energy
- The following is anticipated for end May 2006.
Murray Pump Station Site - 10% Complete
Murray to Anabranch Hall - 60% Complete
Main Line
From Murray to Tara Downs (Main Spurline) approx 21 km.
Spurlines
Warrananga (Moorna) complete
Oakbank (Main) complete
Tara Downs (Garwelt) complete
Warrananga (Garwelt) complete
Tara Downs Spur Line to be approx 50% complete (approx 5 km) - Map of Anabranch Private Irrigation District and Pipeline route
This Map will be updated on a monthly basis and will reflect progress in pipeline construction
Consultation Activities:
Extensive consultation has previously been undertaken over the 10 year development of the Darling Anabranch Management Plan (DAMP) and the Environmental Impact Statement (EIS) for the pipeline.
Throughout the development of the Construction Environmental Management Plan (CEMP) for the pipeline, consultation was undertaken. The CEMP has been prepared with the consultation of many Government Agencies, Council and other stakeholder involvement.
Consultation has involved:
- Anabranch Landholders – 24th February 2006 - Community Meeting to discuss Construction Methodology and Community Consultation processes
- Department of Environment and Conservation –15th March 2006
- Indigenous Heritage Management Sub - Plan
- Flora and Fauna Management Sub - Plan
- Dust Management Sub – Plan - 6th April 2006
- Wentworth Shire Council – 23rd March 2006
- Various aspects of the CEMP
- Construction Traffic Management Sub - Plan
- Soil and Water Management Sub - Plan
- Flora and Fauna Management Sub - Plan
- Barkindji Elders Councils
- Dareton – 23rd March 2006
- Menindee – 29th March 2006
- Department of Primary Industries (formerly NSW Fisheries) – 31st March 2006
- Parts of the CEMP related to Watercourse crossings and River Bank works
- Department of Natural Resources - March and April 2006
- Review and involvement in entire CEMP document
Ongoing consultation will occur throughout the construction of the pipeline and associated works. Amanda Mitchell, Mitchell Australasia, will be liaising with the landholders during the construction stage. For additional information, contact Mitchell Australasia on Ph: (03) 5735 4444.
There will also be future landholder consultation with the E Flows Committee and the In-Stream Sub-Committee determining environmental flows for the Anabranch and the removal of the in-stream structures.
Work Schedules:
The critical construction dates are estimated as:
| Activity | Timeframe |
|---|---|
| Pipe & Fitting Delivery | 01 May 2006 - 01 December 2006 |
| Pipe Installation | 15 May 2006 - 15 December 2006 |
| Pump Station | 16 May 2006 - 15 December 2006 |
| Water Treatment Plants | 16 May 2006 - 15 December 2006 |
| Storage Tanks | 16 May 2006 - 15 December 2006 |
Updates will be based on outcomes from monthly Contractor meetings and monthly program / schedule updates. Copies of bi-monthly newsletters from the Proponent to the Anabranch landholders and other consultation activates are documented.